Share on

From RFQ to First Container: Steps, Documents and Timing for Frozen Seafood from Vietnam

News

CN

Tbes Editorial Team

In short: a first container of frozen seafood from Vietnam passes nine steps: RFQ, specification and price, samples and plant documents, contract, production, inspection and health certificate, booking and stuffing, shipping documents, and arrival clearance. Production usually takes a few weeks. Ocean transit to Northern Europe runs about 30 to 45 days, so a first order placed today lands in the new year.

This page is for import and purchasing managers who are opening a new Vietnamese supplier. It lists what to send in the RFQ, what each step produces, and where first orders usually lose time. Price basis is covered in our guide to FOB, CFR and CIF for reefer containers.

What should an RFQ for frozen seafood contain?

A quote can only be as exact as the request. Ten lines are enough for the supplier to price without guessing, and every missing line triggers a round of questions that costs days. Send the product with its scientific name, the form (fillet, whole, peeled, headless), the size grade, the glaze percentage you accept, the pack and carton weight, the volume in containers or tonnes, the destination port, the price basis, the target ship date and the certificates you need.

RFQ checklist for a first frozen seafood order
LineExample of a complete answerWhat goes wrong if missing
Species and formPangasianodon hypophthalmus, skinless fillet, well-trimmedQuote for the wrong cut or trim level
Size gradeFillet weight range per piece, in grams or ouncesYield and price are not comparable
Glaze and net weightGlaze percentage stated separately, net weight excluding glazePrice per kilo of fish, not of ice, is unclear
PackIQF in bags, or block, with carton weight and units per cartonPackaging order starts late
VolumeOne 40 ft reefer, or tonnes per monthSupplier cannot tell trial from programme
Destination and price basisRotterdam, CIF, or FOB Vietnamese portFreight and insurance are left out
Ship date and certificatesTarget vessel week; health certificate, origin proof, test reportsBooking and paperwork run late

What are the nine steps, and what does each one produce?

Think of the order as a chain of documents. Each step ends with a paper or a file the next step depends on. If the chain is clear from the start, the first container moves at the speed of production and shipping and not at the speed of email.

From RFQ to arrival clearance
StepWhat happensDocument or output
1. RFQBuyer sends the ten lines aboveRFQ email or form
2. Specification and priceSupplier confirms spec, packing and a price on a stated basisQuotation and draft specification sheet
3. Samples and plant papersBuyer checks samples and the plant's approvals, test reports and audit certificatesSample report, plant approval list, certificates
4. ContractSpec, price, quantity, shipment window, payment terms and claims period are agreedProforma invoice or sales contract
5. ProductionRaw material intake, processing, freezing, packing, cold storageProduction record, product tests
6. Inspection and health certificateThe official inspection body samples the shipment and issues the export health certificateHealth certificate
7. Booking and stuffingReefer is booked, pre-cooled and loaded; seals and temperature are recordedBooking confirmation, stuffing record, seal numbers
8. Shipping documentsBill of lading, invoice, packing list, origin proof, insurance if CIFDocument set to the buyer or the bank
9. Arrival clearancePre-notification, border control checks, customs release, delivery to cold storeImport declaration, border control decision

Where does the health certificate fit?

For the European Union, the Vietnamese competent authority NAFIQPM oversees seafood exports, and each export shipment is evaluated, sampled and issued a certificate. This is the step buyers underestimate. The certificate follows the lot, not the supplier, so it cannot be prepared before the goods are finished and tested. Ask the supplier when the sample is drawn and how many working days the lab takes, then fix the vessel date after that, not before. Buyers in the EU can see how the certificate links to the arrival checks in our guide to importing seafood from Vietnam into the EU. Other markets use different certificate forms, which we confirm per destination.

How long does it take?

The ocean leg is the one number you can check against public schedules. Forwarder route data shows the quickest Ho Chi Minh City to Rotterdam sailing at about 30 days, while a forwarder rate listing shows around 40 days for regular services. Transhipment, port congestion and blank sailings add to that. Production and inspection come before the sailing, and arrival clearance comes after it. The planning ranges below are typical for a first order of standard product and are confirmed order by order.

Planning ranges for a first container (typical, confirmed per order)
PhaseTypical durationMain variable
RFQ to signed contract1 to 3 weeksSamples and plant document review
Production to cold store2 to 4 weeksRaw material season and packaging lead time
Inspection and health certificateAbout 1 weekLaboratory turnaround for the shipment sample
Ocean transit to Northern EuropeAbout 30 to 45 daysRoute, transhipment, blank sailings
Arrival clearance1 to 5 working daysBorder control check type and customs

Add the phases and a first container to Northern Europe takes roughly twelve to sixteen weeks from RFQ to the buyer's cold store. For nearer destinations in Asia the sea leg is days, not weeks, and the other phases set the pace.

Where do first orders lose time?

Three delays repeat. The first is a spec that changes after the contract, such as a different trim or carton, which restarts packaging. The second is label text sent late, because artwork and printing sit on the critical path. The third is a certificate wording mismatch between the health certificate and the buyer's own import papers. All three are avoided by sending the final label text and your broker's document list with the signed contract. The steps just before sealing are in our EU shipment readiness checklist.

Questions buyers ask

How small can a first order be?

One full reefer container is the practical unit for sea freight, because a part load changes cold chain risk and cost per kilo. Smaller trials can be discussed for samples and for markets served by consolidated shipments.

Do we need to visit the plant before the first order?

A visit is welcome but not required. Many buyers start with samples, plant approvals and audit certificates, then send a third-party inspector for the first loading. We can share the document set in step 3 before you decide.

Which payment terms are normal for a first container?

Telegraphic transfer with a deposit and a balance against shipping documents, or a letter of credit, are the usual choices for a new relationship. The terms are written into the contract in step 4.

What do we send TBESFOOD to start?

Send the ten RFQ lines, even if some are open. We reply with a specification sheet and a price on the basis you name. Contact us to start.

Sources

Vietnam Agriculture, Latest update on EU market seafood import regulations, accessed 20 Nov 2026.

Fluent Cargo, Vietnam to Netherlands by container ship, accessed 20 Nov 2026.

Voltrans Logistics, FCL rate listing Ho Chi Minh City to Rotterdam, accessed 20 Nov 2026.

Last updated: 20 November 2026. By Tbes Editorial Team.

Let's Talk

Our team is available to answer your questions. Please fill out the form and we'll be in touch shortly.

*Please share the details of your request, and if applicable, the specific product you're interested in.

Email us

export@tbesfood.com

Call or WhatsApp

+84 932 072 978

TBESFOOD COMPANY LIMITED

A member of TBES Group

Head Office: 2nd Floor, 81 Cach Mang Thang 8 Street, Ben Thanh Ward, Ho Chi Minh City, Vietnam

Branch: 62/29C Lam Van Ben Street, Tan Hung Ward, Ho Chi Minh City, Vietnam

Factory: Lot C1.1, Cau Cang Phuoc Dong Industrial Zone, Hamlet 5, Phuoc Dong Commune, Can Duoc District, Long An Province

Lao Factory: Lao Yeast Factory, Ban Naphasouk, Xaythany District, Vientiane Capital, Lao PDR

TBES FOOD PTE. LTD.

Singapore Address: 470 North Bridge Road, #05-12, Bugis Cube, Singapore 188735

Sister brands: TbesAgri frozen fruit · TBESBY brewer's yeast · Lao Yeast Factory industrial ethanol

© 2016–2026 TBESFOOD COMPANY LIMITED. All rights reserved.

EspañolPrivacyCookie settings
FacebookEmailWhatsApp

TBESFOOD COMPANY LIMITED, a member of TBES Group